Chubb Street Improvements + McGregor and State Street Patching

Chubb Street work includes removal of non-functioning rails, street and ADA sidewalk improvements along with a new railroad crossing installed by Union Pacific Railroad. Vehicle and pedestrian access to the street will be closed at this time as installation of the crossing takes place. The railroad crossing is scheduled to start June 20th, 2016. Access to adjacent businesses will be interrupted for short periods during this time. We ask for cooperation of citizens and business owners as the contractors work to construct the improvements as quickly and efficiently as possible

McGregor and State Street patching work includes removal of non-functioning rails, new railroad approaches, street and ADA sidewalk improvements. Vehicle and pedestrian access to the street will be closed at this time.

Project Updates:
June 16, 2016

Project Newsletter_Chubb_June 2016